Marsa Power Station non-compliance with IPPC permit

Email item Email item Print item Print item

1st Gozitan on national executive of Malta Bands AssociationThe Malta Environment and Planning Authority said that it has been notified by Enemalta Corporation that three of the four plants at Marsa Power Station (MPS) have now exceeded 20,000 operational hours.

The Authority said it is currently assessing the situation and appropriate actions, including further mitigation measures, which may be undertaken by Enemalta due to non-compliance with the IPPC permit.

In 2009, MEPA granted an IPPC permit for the Marsa Power Station. Amongst other conditions, the IPPC permit stipulates emission limit values for dust, sulphur dioxide and nitrogen oxides.

Permitted emission limit values must be compliant with the Large Combustion Plants Directive 2001/80/EC (LCPD). Malta had applied the limited lifetime derogation under Article 4(4) (a) of the LCPD.

  • Permalink: Marsa Power Station non-compliance with IPPC permit
  • You may also like...